The project required the excavation and installation of a new waterproof reinforced concrete basement to support a five story student accommodation building.
Project Description
56 metre extension to existing building and inspection pit
Modification to the existing structure to raise the roof height for the provision of OLE
The project required the excavation and installation of waterproof reinforced concrete basement to support a five story student accommodation building.
Project Description
Removal of existing rail and rubble from site, along with other associated works to prepare ground for piles
Installation of CFA piles for pit & shed extension
Installation of driver platform foundations, adjacent to new sidings roads
Construction of new apron slabs, to building entrance & exit
Excavation & preparation for structural pit works
Reinforced concrete structural works, for pit & shed construction